£11 billion of offshore wind, 1.125 million tonnes of stone and a grid link due after 2030

A line of steel electricity pylons stretches across the fields of Haverlands near Ousefleet

£11 billion is the announced investment in two Dogger Bank South wind farms. To help carry their power inland, National Grid proposes a 90 km line from North Humber to High Marnham. Its plans estimate 32,100 tonnes of foundation concrete, 8,700 tonnes of pylon steel, 4,073 tonnes of aluminium conductor and 94 tonnes of overhead fibre-optic cable. There would be nine temporary construction compounds and about 1.125 million tonnes of stone for haul roads, compounds, work areas and highway works.

Four grid projects on this pathway come to about £2.1 billion on the published figures. With the two wind farms and the named solar and battery schemes, the wider investment comes to £18.8–£19.0 billion before further schemes and equipment replacements. National Grid cites Clean Power 2030 in its case for the line. Its own programme puts the line into commercial operation in the final quarter of 2031. The offshore developers expect Dogger Bank South West in 2031 and East in 2032.

Existing steel pylons carrying electricity across fields near High Marnham in Nottinghamshire
Existing pylons near High Marnham, Nottinghamshire. Mat Fascione / Geograph · CC BY-SA 2.0.
Rows of offshore wind turbines seen from the Lincolnshire coast
Lincs Offshore Wind Farm, photographed in 2013. Mat Fascione / Geograph · CC BY-SA 2.0.

Dogger Bank South investment and dates · National Grid project description, Tables 4.2–4.3 and §4.11 · National Grid’s case for the line, §3.3 · Project-by-project cost figures

By Shane Oxer

Cover photograph. Existing pylons across Haverlands near Ousefleet, 2019. Pylons Marching North by Neil Theasby / Geograph, CC BY-SA 2.0.

What National Grid would build through the countryside

National Grid submitted the overhead-line application on 16 October 2026. The Planning Inspectorate accepted it for examination on 12 November. A decision on development consent comes after the examination and recommendation to the Secretary of State. The case reference is EN020034.

12 November acceptance letter · Planning Inspectorate case and filed plans · National Grid proposals and consultation map

Existing steel lattice pylons at the River Ouse crossing near Yokefleet
Existing River Ouse crossing near Yokefleet, photographed in 2017. Graham Hogg / Geograph · CC BY-SA 2.0.

The proposal is for two 400,000-volt circuits on one overhead route between Birkhill Wood, near Cottingham, and High Marnham in Nottinghamshire. The filed schedule shows 245 new pylons on the main route and 22 additional permanent structures to rearrange existing lines near Brantingham and Broomfleet and between Ealand and Keadby. That is 267 new permanent overhead-line structures in this application, including four low-height supports. The main route would also reuse 11 existing pylons over about 3.9 km.

The main route’s new pylons include 181 suspension, 62 tension and two terminal structures. National Grid describes 50–60 metres as typical. The two proposed River Ouse crossing pylons are each listed at 128.6 metres, with the draft design allowing up to 148.6 metres. The two pylons that would tie Birkhill Wood into an existing circuit sit in a separate application.

Before the wires go up, contractors would need to strip and store topsoil, build temporary tracks and working areas, widen some roads and field entrances, and put traffic measures in place at crossings. National Grid’s estimate reaches around 626 full-time-equivalent workers across the route at peak. Local roads, farms and footpaths can be affected well before a pylon is erected, and reinstatement can continue into 2033.

Filed pylon schedule, including 4AF77 and 4AF78 · Environmental Statement §§4.7 and 4.11 · Birkhill Wood tie-in works

Two substations for the line. Four across the linked works.

A substation is where circuits meet. Its switches let National Grid direct power and take equipment out of service safely. Transformers allow electricity to move between different voltages. The new line would end at Birkhill Wood and High Marnham. The Brinsworth–Chesterfield–High Marnham upgrade also uses High Marnham and adds two other substations. High Marnham appears once in the count.

New substationWhat it does and what the plans show
Birkhill Wood, East RidingThe 400 kV northern end of the line and intended connection for three offshore wind farms. Most switchgear is housed indoors. The options study models 25 bays, the positions where circuits or equipment connect. The first contract covers detailed design and enabling works. National Grid targets commissioning in Q2 2030 and third-party connections in Q4 2030. Programme · Contract award
High Marnham, NottinghamshireSouthern end and connection to the existing network. The 400 kV compound measures about 690 by 200 metres and includes 16 bays, 10 gantries, 20 permanent buildings and two large transformers rated 1,100 and 150 MVA. National Grid gives a winter 2029 operating target. Programme · Engineering plans
Calow, near ChesterfieldA new 400 kV substation for the uprating, with plans for three supergrid transformers. The separate proposed Chesterfield–Willington line would start here. National Grid plans
Long Lane, near WhistonA new 400 kV substation for the Brinsworth end of the uprating, with switchgear and gantries to connect to the overhead lines. Whitestone’s developer identifies it as the proposed connection for the solar and battery scheme. National Grid plans · Whitestone proposal

The uprating would raise two existing double-circuit routes from 275 kV to 400 kV. M Group describes around 70 km of overhead-line upgrades and substation work. National Grid confirmed local planning permission for the three uprating substations in August. Ofgem’s licence gives the uprating a delivery date of 31 December 2029. Chesterfield–Willington, a separate reinforcement of about 60 km, has a licence date of 31 December 2031.

Other existing circuits help carry power away from High Marnham. National Grid plans to replace wires on sections between West Burton, High Marnham, Stoke Bardolph and Ratcliffe-on-Soar, and between Cottam and Staythorpe. Its published programme targets completion in 2028.

Brinsworth–High Marnham works · National Grid’s August approvals update · Ofgem’s decision and licence dates · Chesterfield–Willington proposals · West Burton and Cottam circuit programme

December 2031 is already in the plans

WorkScheduled window
Site mobilisationQ2–Q3 2028, subject to consent
Access and enabling workQ2 2028–Q2 2030
FoundationsQ2 2028–Q3 2030
Pylon assembly and erectionQ4 2028–Q1 2031
Stringing the wiresQ1 2029–Q3 2031
Testing and commissioningQ2–Q3 2031
Commercial operationQ4 2031
ReinstatementQ1 2031–Q2 2033
National Grid’s indicative programme for the new Humber line

National Grid must secure land access and procure equipment, and it must plan temporary outages while keeping the existing grid working. Flood zones and seasonal restrictions also affect when crews can work. With wire installation and testing scheduled into the third quarter of 2031, a delay on critical works or a missed outage could push commercial operation into 2032. That is a risk. The filed target remains the end of 2031.

Clean Power 2030 is a national target. In a typical weather year, the Government aims for clean sources to make up at least 95% of Great Britain’s generation and to produce at least as much electricity over the year as Britain consumes. NESO, the National Energy System Operator, lists both the new Humber line and Chesterfield–Willington among projects due after 2030 that would help if brought forward. It puts the Brinsworth–High Marnham uprating among the key works for 2030. In its two scenarios, missing that uprating added £220–£222 million in modelled costs in 2030 for managing grid bottlenecks and reduced the clean-power share by 0.9–1.0 percentage points. Ofgem says a delay to the uprating would likely delay the other two schemes.

On the published dates, the full package of new wind generation and grid capacity described here will miss 2030. Ministers should say how much of it their 2030 calculations assume, and where the power would go if the inland upgrades run late.

Construction programme, Table 4.2 · NESO’s 2030 advice, Annex 2, Tables 2 and 4 · Ofgem on dependencies and outages, §§2.3–2.5 · Clean Power 2030 Action Plan

When can the wind farms actually get power out?

Start at sea. Dogger Bank South East and West have consent for up to 200 turbines and 3 GW combined. The export cables come ashore near Skipsea, then run about 32 km inland to converter stations near Bentley. The stations convert direct current to alternating current for the grid. A further underground connection leads to Birkhill Wood. The developers expect to start main converter construction in summer 2027 and are aiming for a final investment decision that year.

Nothing will work at full scale until the whole route can carry the power. Turbines, sea cables, land cables, converters, substations and the onward grid must work together to deliver the full output. Some power could travel over existing circuits earlier. That depends on how much spare capacity NESO can make available and the terms of each connection.

The 13 November NESO capacity register lists 400 MW for each Dogger Bank South project on 30 October 2030, followed by another 1,050 MW each on 30 November 2031. These are dated capacity entries. The developers’ commissioning targets are 2031 for West and 2032 for East. A third wind project, Dogger Bank D, has a separate 1,450 MW register entry at Birkhill Wood dated 31 October 2031. Its proposal is for up to 1.5 GW. The works register lists the new Humber line for all three.

The two Dogger Bank South projects won Contracts for Difference at a £91.20 per megawatt-hour strike price in 2024 prices, with a 2030/31 delivery year in the auction results. The contract pays the generator the difference when the market reference price is below the strike price. The generator pays back the difference when it is above. The contract date, connection-register date and developer commissioning date answer three different questions.

Dogger Bank South consent · Skipsea to Bentley cable statement · Bentley construction programme · Developer investment decision timetable · Developer commissioning dates · Dogger Bank D proposal · NESO capacity register · NESO works register, scheme 100818-201654 · Government auction results · How the contract pays

Which solar farms and batteries connect where?

Whitestone proposes to use Long Lane at Brinsworth, with a 750 MW connection shared between solar generation and batteries. Its application gives 2029 as the earliest operating date, subject to consent and delivery of the connection. Fenwick has consent to connect at Thorpe Marsh and a 237.5 MW capacity-register entry dated 16 April 2032. Fidra’s Thorpe Marsh battery is a separate project at the same grid site. Fidra targets commercial operation in 2027, and its other battery at West Burton C targets 2028. Different projects can use different circuits and have different restrictions.

One Earth has a 740 MW entry dated October 2029 at High Marnham and its own local connection agreement. National Grid told its examination that the new Humber line is designed to increase transfer between northern England and the Midlands. Local projects still need their own connection and capacity to export. The Cottam, Gate Burton, Tillbridge and West Burton solar developments overlap along parts of their cable corridors, which also means overlapping construction in some places.

NESO’s works register lists the Humber line against some projects with much more distant connection points. In the 13 November snapshot, examples include Norton in 2031, Derwent at Thornton in 2032, Housham at Navenby in 2033, Stallingborough at Grimsby West in 2034 and Monk Fryston Energy Park in 2035. A grid work can show up in more than one project’s list because it affects the wider network.

Beacon Fen connects at Bicker Fen. Its £550 million sits outside the Humber estimate. So do Tween Bridge, whose £820 million funding estimate relates to a connection on the Drax–Keadby route, and Grimsby–Walpole, a separate 140 km reinforcement for which National Grid’s preferred option was priced at about £2.11 billion and whose project page targets full operation by 2033.

Whitestone’s filed programme, §5.5.1 · Fenwick consent and connection · Fidra’s project dates · National Grid’s One Earth examination evidence · Tillbridge planning statement, §6.17 · NESO works register · Beacon Fen’s Bicker Fen connection · Beacon Fen funding estimate · Tween Bridge Funding Statement · Grimsby–Walpole option cost, Table 6.13 · Grimsby–Walpole programme

Where the money goes

Start with the four grid works. Their published figures add up to roughly £2.11 billion, using £1 billion for the Brinsworth–High Marnham uprating because the contractor’s description gives a figure above that threshold. Each figure comes from a different document. They cover different stages of design and use different price years.

Grid worksPublished figureWhat the figure covers
North Humber–High Marnham£734.2mNational Grid’s 85 km options model, comprising £459m for the circuit and £275.2m for modelled substation works. The latter includes two bays at High Marnham on an assumed new substation. The filed route is about 90 km. Table 6.1
Brinsworth–High Marnham via ChesterfieldOver £1bnM Group’s description of the uprating. Ofgem confirms the forecast has risen since 2022 and keeps the cash figures in a confidential annex. Contractor description · Ofgem decision
West Burton and Cottam circuits£157.8mNational Grid’s forecast for strengthening existing circuits that help carry power onward. The £12.039m Ofgem preconstruction allowance relates to the same works. Ofgem annex, Table EA2
Chesterfield–Willington£220.6mPreferred option based on a 51 km model and terminal works at 2020/21 prices. Options report, Table 8.1

The £11 billion offshore announcement and those grid works bring the running total to about £13.1 billion. The named inland projects add £5.67–£5.93 billion, taking the combined figure to £18.8–£19.0 billion.

Grid siteSolar and battery projectsSubtotal
Brinsworth / Long LaneWhitestone £500–£600m.£500–£600m
Thorpe MarshFenwick £316–£325m and Fidra’s battery £700m in project capital.£1.016–£1.025bn
High MarnhamOne Earth solar and batteries £950m–£1.05bn.£950m–£1.05bn
CottamCottam Solar £850–£900m, Gate Burton £525m and Tillbridge £700m.£2.075–£2.125bn
West BurtonWest Burton Solar £500m, Steeple £380m and Fidra’s West Burton C battery £250m.£1.13bn
Published investment figures at the inland grid sites

Several solar estimates already include batteries and their own connection works. Thorpe Marsh’s £594 million in debt facilities forms part of its financing and adds no second project. Some public figures include land, contingencies or financing. Shared infrastructure can serve several schemes. A single audited total would require all the estimates on a common price basis, with each shared cost traced to the work it pays for.

The wind developers’ earlier planning statement used £12.4 billion for the same two wind farms, including financing and operation. The calculation here uses their later £11 billion announcement. The earlier estimate illustrates how much the scope and basis of a published number can change.

Thorpe Marsh financing case study · Dogger Bank South Funding Statement, paragraphs 36–37 · January 2026 investment announcement

How it could pass £20 billion

There are three more physical battery proposals at the substations already discussed. Almholme at Thorpe Marsh proposes a 1,025 MW battery that can discharge at full power for about two hours, plus 49.9 MW of solar. Crabtree Lane at High Marnham proposes 1,000 MW for four hours. Field High Marnham proposes up to 400 MW. The duration matters because a battery able to discharge for four hours holds twice as much energy as a two-hour battery of the same power.

Battery proposalIndicative investment
Almholme, battery alone£356–£516m
Crabtree Lane, four hours£539–£704m
Field High Marnham, assuming two hours£139–£201m

Using published battery benchmarks, those three could add £1.03–£1.42 billion, bringing the named build-out to £19.8–£20.5 billion. This uses the developers’ and council’s published equipment sizes and a two-hour assumption for Field, whose duration remains unverified. Almholme’s solar is outside that calculation. The figures are our estimates based on comparable equipment.

If Dogger Bank D also goes ahead, a £5.5–£7.5 billion comparison for a wind farm of its size takes the same scenario to £25.3–£28.0 billion. That comparison scales the two South projects’ announced investment and uses the filed range for another 1.5 GW North Sea project. Dogger Bank D’s own construction budget remains unpublished in the records reviewed.

Almholme proposal · Bassetlaw’s Crabtree Lane report · Field’s High Marnham application evidence · Two- and four-hour battery benchmarks · Dogger Bank D proposal · Outer Dowsing funding comparison, paragraph 17

The equipment will have to be replaced

Fenwick’s application gives its batteries and inverters 10–15 years and assumes some replacement work every ten years. It gives its solar panels 25–40 years. Whitestone’s application gives its batteries 5–15 years and panels 25–40 years, within a proposed 60-year operating period for the site. Dogger Bank South’s design life is about 30 years. These schedules put battery and inverter replacement well ahead of a full solar-panel or wind-farm renewal.

To put a figure on it, a single renewal at Fidra’s Thorpe Marsh and West Burton C battery sites together would be around £450–£765 million using two published battery cost benchmarks and a replacement assumption of 80% of the comparable cost of a new battery system. For solar, applying the panel share from Arup’s study for the Government to its construction benchmarks gives an illustrative £97–£138 million for the modules per gigawatt of installed panel capacity, at the study’s price basis. Taking out the old panels, installing the new ones, testing and disposal add further costs. An actual budget needs the size and renewal schedule of each site.

Fenwick Environmental Statement, chapter 2 · Whitestone Environmental Statement, APP-057, Table 5.10 · Dogger Bank South design life · Battery costs · Year-15 battery replacement assumption · Arup solar costs, Tables 41 and 43

What billpayers and communities need to see

When transmission lines fill up, the system operator can pay a generator to cut output and pay for replacement power elsewhere. NESO reported £2 billion in these grid constraint costs across Great Britain in 2025/26 and forecasts £3.9 billion in 2027. Its higher 2030 scenarios reach £6.8–£7.7 billion if generation broadly follows the Clean Power plan, grid works stay on their planned timetables, and gas and carbon prices are high. Those are national costs. The investment totals above measure spending on named schemes. To work out the impact on bills you also need network charges, wholesale prices, support payments, savings and the cost of any delay.

The National Audit Office cites an Ofgem estimate of up to £70 billion for Great Britain’s transmission network between April 2025 and March 2031. It found the Government had yet to demonstrate that its chosen grid upgrades were the best way to meet its objectives without an integrated spatial plan or a whole-system appraisal. The network industry’s growth plan estimates £58 billion in economic value by 2035 and around 210,000 direct and indirect jobs supported across the sector in 2035. Those are national projections of economic activity. The local question is how many contracts and jobs will go to people and businesses along this route.

National Grid says the Humber project could provide a community fund of around £18 million if consent is granted. Separately, the Government lists the line among projects expected to qualify for its electricity bill discount scheme, which offers eligible households within 500 metres of qualifying infrastructure £250 a year for ten years, or £2,500 in all.

NESO constraint costs and assumptions · National Audit Office report · How network costs enter bills · Electricity Networks Sector Growth Plan · National Grid’s community fund · Government bill discount and expected eligible projects

Publish one costed delivery programme for this corridor. Show when each substation and line can carry power, how much each project can actually export before the upgrades are complete, who pays for shared works and replacements, and what a slip into 2032 would cost. People living with the construction and paying electricity bills should be able to find those answers in one place.

We are calling for the Climate Change Act targets to be suspended while a full national impact assessment is carried out. Read and sign the parliamentary petition.