A mass of maybes — and a ginormous financial risk.
Hope to Save Our Countryside | 24 November 2026
People need cheaper energy. It really is that simple.
Yet British households owe more than £5 billion in energy debt and arrears. Ofgem’s figures put the total at £5.02 billion in June 2026. People are struggling to keep warm. Cold homes can endanger health and lives.
Now consider what is proposed in Scotland: a project costing more than £1 billion to move carbon dioxide from industry and power stations and bury it beneath the North Sea. That is the reported cost of the proposed transport and storage development, not the cost of all the equipment needed to capture the gas in the first place.
From little Acorns come the mighty Oak. And in this case, a mass of maybes and a ginormous financial risk.
How much will it cost, why does it consume so much energy, and who is going to pay?
What will it cost just to bury carbon dioxide?
Acorn is designed to store five to ten million tonnes of CO₂ a year, but it is not an operational commercial storage network. The industry’s own report, Offshore Energies UK, October 2024, page 13, Figure 5, provides a breakdown of estimated costs.
| What you are paying for | Cost per tonne | At 5 million tonnes a year |
|---|---|---|
| Capture | £80–£120 | £400–£600m |
| Transport | £20–£25 | £100–£125m |
| Underground storage alone | £15–£20 | £75–£100m |
| Transport and storage | £35–£45 | £175–£225m |
| Entire process | £115–£165 | £575–£825m |
Just storing five million tonnes could cost the equivalent of £75–£100 million a year. Moving and storing it could cost £175–£225 million. The whole process could cost £575–£825 million a year. At ten million tonnes, those figures double: £150–£200 million for storage alone and £1.15–£1.65 billion for the whole process.
Approximate 2024 OEUK component estimates multiplied by five million tonnes. Not an Acorn tariff, operating budget or subsidy commitment.
These are illustrative cost equivalents, not Acorn-specific forecasts or a bill for taxpayers. Do not add the reported £1 billion development cost to the cost equivalents without establishing what they include. Actual costs will depend on the facilities, distances, volumes and financing; the industry expects costs to fall as deployment grows. Acorn’s actual price per tonne has not been established in the evidence examined.
Why use so much energy to capture carbon?
SSE’s March 2026 Peterhead project document says the proposed gas station would have a capacity of up to 910 MW, but only about 750 MW net electrical output because of the energy needed for capture.
Source: SSE March 2026 FAQ. Proposed design values, not actual operating results.
160 MW. Nearly 18% of the stated generating capacity. At those outputs for one hour, the difference is 160,000 kilowatt-hours. At an illustrative 50% of annual hours, it amounts to about 701 million kilowatt-hours. Conventional stations also have auxiliary loads, so this gross-to-net comparison is not a measured incremental annual loss.
The process needs energy to separate carbon dioxide from exhaust gases, regenerate chemicals, compress the gas and move it underground. A simple example: a station operating at 60% efficiency would need 1.67 units of gas energy to deliver one unit of electricity. At 50% efficiency it needs two units — 20% more gas. At £30 per megawatt-hour of gas energy that means £10 more fuel for every megawatt-hour of electricity. These are illustrative assumptions, not actual Peterhead fuel figures.
SSE estimates Peterhead could capture 1.5 million tonnes annually. Applying the same industry benchmarks implies £22.5–£30 million a year for storage alone and £172.5–£247.5 million for the complete capture, transport and storage chain. These are illustrations, not the station’s forecast; do not add the fuel example on top without checking for overlap.
Remember: this has not been proven at Acorn
These are proposed projects. Not operating results. Acorn has not demonstrated commercial operation at its intended scale, and Peterhead has not demonstrated its projected capture rate, net generation or fuel use in operation. Carbon storage has been demonstrated elsewhere, but it does not prove the economics or performance of this particular integrated scheme. The planned output, operating life, customer volumes and financing are not guaranteed.
And who is expected to pay?
The Public Accounts Committee’s February 2025 report recorded £21.7 billion of government-backed support over 25 years for the first five national carbon capture projects. Roughly 75% was expected to be funded through consumer levies. The report also identified £34.4 billion of maximum contingent liabilities, with a reasonable worst-case estimate of £14.3 billion. These are national figures, not Acorn-specific costs, and must not be added together.
Acorn’s new developer told the Financial Times on 23 November 2026 that development would cost over £1 billion and require further government support. The original £200 million development funding offer was conditional; approximately £12 million in grants has been provided under it. The Government now proposes loans or equity subject to business-case approval and an intended return for the taxpayer.
Companies can earn storage fees and save on carbon allowance charges. Those are real financial transactions. But a subsidy is expenditure to whoever funds it. An estimated monetary value of avoided emissions is not cash in a household’s bank account. Separate the cash costs, revenues and modelled environmental benefits.
Why are we doing this when people are suffering?
The Government’s stated aim is to reduce emissions while retaining industry and dependable power. Carbon capture can reduce emissions, but the costs and alternatives need to be evaluated alongside that benefit. The question is how much people will ultimately pay for each tonne avoided, and whether the same benefits can be delivered at lower cost.
And that is before examining MarramWind, a proposed 3,000 MW floating wind farm in partially overlapping offshore territory. The January 2026 UK floating offshore wind auction price was £216.49 per megawatt-hour in 2024 prices — more than double the Scottish fixed-bottom offshore wind price. MarramWind has not been awarded that price; its costs must be assessed separately.
People cannot heat their homes with carbon valuations. They need affordable electricity and gas.
The evidence below is for anyone who wishes to examine our findings: the ownership, funding, planning and seabed issues, photographs, charts, primary records and cost comparisons.
Detailed evidence and source documents
1. Follow the money: what has EnEarth actually bought?
The 23 November company announcement describes an agreement to acquire Storegga’s interest and lead-developer position, subject to completion conditions. The Financial Times report identifies further government investment as necessary. The company originated from Greek energy group Energean; its current ultimate ownership and funding commitments should be disclosed rather than assumed.
| Partner | Share after proposed completion |
|---|---|
| EnEarth | 30% |
| Shell | 30% |
| Harbour Energy | 30% |
| North Sea Midstream Partners | 10% |
Source: NSMP’s December 2021 ownership announcement and EnEarth’s acquisition announcement. NSMP has infrastructure-investor backing, including Wren House and institutional investors advised by J.P. Morgan. A purchase of shares does not establish that the partners have committed the full capital for construction.
2. The £200 million promise and the £31.25 million write-down
The UK Government announced up to £200 million in development support in June 2025, conditional on affordability, readiness and business-case approval. A November 2026 parliamentary answer puts grants provided at about £12 million. The 30 October ministerial answer confirms that subsequent support is intended to take the form of loans or equity investment, with a return sought for the taxpayer.
The remaining £188m is not an unconditional entitlement. This is not a ledger of all historical public funding.
Meanwhile, Macquarie Investments 1 Limited’s 2025 financial statements, subsequent events and Note 25 record a November 2025 impairment of £31,253,167 in Storegga after difficulties with its funding round. This is a write-down of its investment in the company, not a finding that Acorn itself is insolvent. Storegga subsequently announced a sale process for its Acorn stake.
| Date | Documented development |
|---|---|
| 2021 | Acorn passed over for initial Track 1 selection; reserve status |
| 2023 | Selected to enter Track 2 |
| June 2025 | Up to £200m conditional development funding announced |
| November 2025 | Macquarie impairs its Storegga investment |
| December 2025 | Storegga launches sale process |
| October 2026 | Government changes proposed future support to financial transactions |
| 23 November 2026 | EnEarth acquisition agreement announced |
| Around 2029 / early 2030s | Reported indicative investment decision and operating timetable, not guaranteed delivery |
Government equity may offer an upside; loans may be repaid. But a publicly financed return must be assessed net of the subsidies, guarantees and contingent liabilities supporting the business.
3. Floating wind: the cost of electricity

MarramWind proposes up to 3 GW, up to 225 turbines, across 684 square kilometres, approximately 75 km offshore. Its design envelope includes turbines up to 350 metres tall. Offshore consent applications were submitted in January 2026. See ScottishPower’s project description and application document library. Its current Gate 2 connection offer and enabling grid programme require independent verification.
Source: DESNZ, 14 January 2026. Floating wind cleared at 2.42 times the Scottish fixed-bottom price. Strike prices are not complete whole-system costs.
The official AR7 results cover 192.5 MW of floating wind, far smaller than MarramWind. Floating wind requires platforms, anchors, moorings, dynamic cables and specialist installation and maintenance. Costs could decline as the industry scales, but the current auction provides a real benchmark rather than an aspiration.
Illustrative MarramWind bill exposure
| Assumption / result | Illustrative value |
|---|---|
| Installed capacity | 3,000 MW |
| Capacity factor | 45% |
| Annual output | 11.826 TWh |
| Hypothetical strike price | £216.49/MWh |
| Reference price assumption | £75/MWh |
| Annual strike-price revenue equivalent | £2.56bn |
| Annual net CfD payment | £1.67bn |
| 20-year undiscounted net CfD payment | £33.46bn |
This is not an awarded MarramWind CfD, a project cost forecast or a government spending commitment. It is an arithmetic sensitivity using 3,000 × 8,760 × 45% hours and a price difference of £141.49/MWh. It excludes variable output, changing reference prices, curtailment, contract exclusions and grid costs. A two-way CfD can require repayment when reference prices exceed the strike price. At the same generation and strike-price assumptions, £100/MWh reference prices imply £27.55bn over 20 years; £150/MWh implies £15.73bn.
4. Carbon capture: more fuel for the same electricity

A post-combustion capture plant needs heat and electricity to separate CO₂, regenerate solvents, compress and dry the gas, transport it and inject it into rock formations. The Government’s 2018 technical review recognises a gas-fired generation efficiency penalty. Carbon capture can reduce direct emissions, but it does not create electricity.
Assumed efficiencies of 60% and 50%, not actual Peterhead guarantees. Equal electricity output requires 60/50 = 1.20 times the fuel, or 20% more.
| For the same 1 MWh of electricity | Conventional CCGT | Illustrative CCS CCGT |
|---|---|---|
| Net efficiency | 60% | 50% |
| Gas input (MWh thermal) | 1.667 | 2.000 |
| At £30/MWh thermal | £50 | £60 |
| Additional fuel cost | — | £10/MWh |
This excludes capture plant capital, maintenance, CO₂ network charges, carbon price savings and upstream methane emissions. The proper comparison is cost per tonne of emissions avoided and cost of reliable power, taking account of all those effects.
5. Peterhead and Acorn: a circular dependency
The Energy Consents Unit decision, ECU00003433 of 27 October 2026 concerns the proposed 910 MW CCGT with post-combustion capture. SSE’s project page describes the intended development. Acorn requires substantial dependable CO₂ throughput; Peterhead requires an available transport and storage route. If increasing wind generation reduces the gas plant’s operating hours, its emissions throughput could also fall.
Gas supply → power station → capture equipment → compression and pipeline → offshore injection → monitoring and eventual closure. Every link adds expenditure and delivery risk. The operational and economic business cases need compatible hourly dispatch, availability and CO₂ flow assumptions.
The Scottish Parliament committee report of 27 February 2026 documents Professor John Underhill’s warning that the loss of Grangemouth and Mossmorran industrial activity could undermine prospective CO₂ supply. Storegga disputed parts of his assessment. That disagreement makes transparent contracted volumes and revised economics particularly important.
A sensitivity illustration, not Acorn’s forecast. It excludes capture costs and assumes the same annual network cost at every throughput.
The network could also attract overseas emitters, potentially improving utilisation and revenues. Any public investment case should disclose whether those users will pay full economic costs and how cross-border liabilities will be allocated.
6. Competing seabed rights
On 19 June 2025 at First Minister’s Questions, Mercedes Villalba challenged John Swinney over the overlapping MarramWind and Acorn rights. The Offshore Wind and CCS Colocation Forum presentation of 2 July 2025 identifies marine surveys, drilling access and monitoring as practical challenges. It also confirms that Acorn shifted its focus towards the depleted Goldeneye field, reducing the overlap. That is mitigation, not proof of an irreconcilable conflict or proof that all issues are resolved.
| Floating wind requirement | Carbon storage requirement |
|---|---|
| Moorings and anchors | Access to wells and drilling vessels |
| Dynamic and export cables | CO₂ pipelines and crossing agreements |
| Long-term turbine maintenance | Geological monitoring and seismic surveys |
| Marine safety zones | Emergency intervention and remediation |
Acorn’s CS003 licence variation, signed 20 October 2026, moved a schedule deadline from November 2026 to May 2027. A storage licence is not itself a final injection permit. We have not established a commercial injection permit or final co-location cost allocation. Shell’s departure from MarramWind in 2025, while retaining its Acorn interest, does not prove any causal link with the overlap.
7. Parliament’s warning: the taxpayer and consumer exposure
The Public Accounts Committee’s February 2025 report records £21.7 billion of support over 25 years for five initial Track 1 projects, and programme contingent liabilities estimated at up to £34 billion. It records the department’s expectation that approximately 75% of early-project support would be financed through consumer levies. The earlier UK programmes were cancelled in 2011 and 2016, and the target of capturing 20–30 million tonnes annually by 2030 was found unachievable in December 2024.
Illustrative allocation of the initial £21.7bn commitment. Not Acorn-specific, not actual spending, and subject to contractual allocation.
The £34 billion figure represents potential liabilities, not expenditure already made; it must not be simply added to the £21.7 billion commitment or the MarramWind scenario. The committee raised serious concerns over the performance of early UK projects and the lack of public profit-sharing in the first contracts. Geological storage has operated overseas for decades, but that does not prove the viability of this particular integrated network.
The government commercial framework includes regulated returns, revenue support arrangements and specified risk protections, including possible compensation in certain discontinuation circumstances. The Government argues that this structure enables early investment and manages risk. Acorn’s own final contracts have not been established. Parliament must know what would happen if customers fail to connect, utilisation falls or injection is interrupted.
8. The full infrastructure ledger: what is still missing?
| Item | What must be independently quantified |
|---|---|
| MarramWind | Turbines, platforms, anchors, cables, maintenance and decommissioning |
| Electricity grid | Offshore and onshore reinforcement, connection dates and constraints |
| Peterhead | CCGT and capture capital costs, fuel and operating expenditure |
| Industrial capture | Equipment at each emitter and associated support |
| SCO₂T Connect | Gas pipeline conversion, conditioning and compression |
| Acorn | Offshore pipeline integrity, wells, injection and storage capacity |
| Long-term storage | Monitoring, closure, remediation, financial security |
| Public exposure | Grants, equity, loans, revenue guarantees and contingent liabilities |
No single public, independently verified whole-system ledger covering all of these components has been identified in this investigation. Separate business cases cannot substitute for the combined affordability assessment. The reported £1bn Acorn figure is not the full cost of the cluster.
9. Questions that require answers before further public commitments
| Question | Evidence required |
|---|---|
| How much public money has already been spent? | All historical grants and development expenditure, by funding body |
| What private capital is actually committed? | Binding construction finance, not acquisition consideration |
| How much CO₂ is contracted? | Minimum volumes, customer contracts and updated industrial demand |
| What is the taxpayer’s downside? | Loan and equity terms, revenue guarantees and maximum contingent exposure |
| Can the projects coexist? | Final seabed agreements, engineering constraints, allocation of costs |
| When can they operate? | Storage permit, physical grid connection and credible integrated construction schedule |
| What alternatives were assessed? | Independent whole-life cost and reliability comparison, including emissions avoided |
From little Acorns grow mighty liabilities
Our criticism is that the country and its people cannot afford to waste money on ideology. The financial case needs to be demonstrated, not assumed from a policy target. What will Acorn actually cost, what is the maximum public exposure, what will it mean for bills, and what alternatives were assessed?
The proposed £1 billion-plus development is only one part of the picture. The capture plants, additional energy, pipelines, storage wells and ongoing maintenance all require resources. The intended environmental benefits must be assessed separately from actual money spent.
From little Acorns grow mighty liabilities. People need affordable energy, not another mass of maybes.
Caveat taxpayer.
Source register and methodology
Primary records: DESNZ AR7 results; Public Accounts Committee CCUS report; National Audit Office CCUS programme; 30 October ministerial answer; November grant answer; Macquarie Companies House filing; EnEarth announcement; NSMP ownership announcement; MarramWind project; Peterhead consent; Scottish Parliament committee report; First Minister’s Questions; Colocation Forum; NSTA licence variation; Government CCS technical assumptions; CCUS investment framework.
News reporting: Financial Times, 23 November 2026; Traders Union article that prompted this investigation. All charts identify their scope; illustrative figures are simple arithmetic scenarios and must not be added to unrelated national liabilities. Photographs depict existing infrastructure and are credited separately.
Additional primary evidence: OEUK CCUS Insight, October 2024, Figure 5, p.13; SSE Peterhead FAQ, March 2026; Ofgem debt and arrears indicators.