PEOPLE ARE FREEZING | Part 3 — NGET: The grid is late. The costs are arriving now.

GB historical boundary reinforcement capacity was 32% below original plans in 2013–2021; £70bn estimated GB transmission investment 2025–2031, not NGET alone. Campaign artwork.

£70 BILLION — WHERE IS THE CAPACITY WE ARE PAYING FOR?

An investment announcement is not an engineering milestone. A construction contract is not an energised substation. An energised asset is not necessarily a completed network capable of carrying the full transfer required. Friday’s investigation asks how the delivery record matches the expenditure authorised by the regulator.

In Wednesday’s opening investigation, we examined the £443 increase in the annualised price cap, from £1,723 to £2,166. Ofgem’s confirmed cost breakdown attributes the immediate increase principally to wholesale costs: the wholesale allowance rose 50%. The system costs investigated here are a separate structural pressure. They must not be presented as the cause of the whole January increase. Ofgem, 25 November 2026: cost breakdown.

TRANSMISSION CHARGES — MORE THAN DOUBLE

Annual transmission network charges, constant 2025 prices

2025/26 — £5.1bn

 

2030/31 forecast — £12.3bn

 

Real increase of approximately 141%. Annual regulated charges, not the £70bn cumulative investment programme.

Source: IFS Green Budget, Electricity prices, 2026

The IFS projects combined network and balancing costs rising by £12bn a year by 2030/31 compared with 2024/25 before expected congestion reductions arrive later in the 2030s. These are forecast annual charges and costs, not an amount to add to the capital programme. IFS analysis.

THE CONNECTIONS DELIVERY RECORD

Share of projects offered the connection date they wanted

2019/20 — 64%

 

2023/24 — 16%

 

NAO reports a fall of 48 percentage points. An offered date is not proof of completed physical capacity.

Source: NAO, September 2026

A REAL PROJECT, A REAL DELAY, A REAL CONSUMER COST

WESTERN LINK — A DOCUMENTED CASE

2,250 MW

Transfer capacity

MARCH 2017 → JUNE 2019

Original expected delivery and actual completion

£158 MILLION

Agreed consumer redress package in 2021

Joint NGET/SPT licence responsibility. Ofgem found supply-chain delays, not that the two companies caused or exacerbated them. Source: Ofgem, 30 November 2021

Western Link is the test case because the regulatory evidence is explicit. Delayed delivery constrained the transfer of Scottish renewable electricity into England and Wales and raised the need for interventions. Ofgem returned part of the redress via lower system charges; the package was not a calculation of all congestion costs arising from the delay.

INVESTMENT RETURNS — WHAT SHAREHOLDERS RECEIVE AND WHAT CONSUMERS GET

National Grid plc’s 5 November 2026 results report accelerating capital investment across its UK and US businesses and an interim dividend of 16.97p per share. The group has announced £70bn of investment over five years across its UK and US Northeast networks. This is a different figure from the NAO’s £70bn GB-wide transmission estimate; the two must not be combined or confused. Group dividends are not NGET’s standalone distributions. National Grid plc half-year results filed with the FCA.

The regulator sets allowed returns to attract capital and determines recoverable expenditure. The test is whether those returns and allowances are aligned with delivery of useful network capacity and whether consumers receive the promised benefits. Publish NGET’s standalone accounts, regulated asset value, allowed and achieved returns, dividends and capital works by project alongside schedule deviations. Without a common reconciliation, shareholders’ returns cannot be reliably attributed to an individual consumer cost.

£70 BILLION OF INVESTMENT — BUT WHEN WILL THE CAPACITY BE READY?

An electricity grid cannot be built by announcing a target. It requires land, planning permission, engineers, transformers, cables, substations and years of construction.

PROMISED VS DELIVERED

GB transmission boundary reinforcement capacity, 2013–2021 (original plan = 100%)

Original plan — 100%

 

Delivered relative to plan — 68%

 

32% shortfall against original GB plans; not NGET alone. FTI did not investigate the causes of this shortfall.

Source: FTI / Energy Systems Catapult, Ofgem-published report, October 2023, pp. 74–75, paras 3.25–3.27

GB TRANSMISSION INVESTMENT ESTIMATE

UP TO £70 BILLION

2025/26 to 2030/31 — multiyear investment estimate, not annual expenditure or NGET alone.

Source: National Audit Office, September 2026; Parliamentary answer, 16 September 2026.

The National Audit Office’s 2026 investigation reports that Ofgem estimates £70 billion of transmission investment is required across Great Britain between 2025 and 2031. This is a multiyear programme, not an annual cost or a figure attributable to NGET alone.

The audit identifies 80 projects in NESO’s original 2024 Clean Power advice, of which 64 remain ongoing. Most were at an early stage of development and were not expected to meet the original dates that NESO considered economically optimal for limiting congestion costs.

NESO identified three projects requiring acceleration for Clean Power 2030 and eight others where earlier delivery would reduce constraints. The NAO found no significant acceleration across those eleven projects at the time of its review.

There is a crucial distinction between a project being announced, having consent, being under construction and actually delivering secure electrical transfer capacity. A contractual or regulatory date is not proof that a completed system can carry the required power.

National Grid Electricity Transmission is responsible for building and operating the transmission network in England and Wales. Scottish transmission owners have their own responsibilities. Ofgem approves regulated investment, NESO assesses system needs, and DESNZ sets policy.

The public needs a clear account of each major project: its original need date, regulatory milestone, revised completion date, expected transfer capacity and the cost consequences of delay. Without that information, it is difficult to determine whether investment is delivering the benefits that justify the charges on our bills.

The NAO also notes that Ofgem expects accelerated network investment to raise network charges but reduce overall bills relative to the higher constraint costs of delayed delivery. This is precisely why the counterfactual matters: the choice is not simply between spending and not spending, but between competing system designs and delivery strategies.

Our campaign is asking for the evidence that the selected route offers value for money against credible alternatives.

Tomorrow, we turn to the regulator and its responsibility to protect consumers.

Evidence: National Audit Office, Upgrading the electricity transmission network; Full NAO report.

Petition: Read and sign Parliamentary petition 780321.

Shane Oxer — Campaigner for fairer and affordable energy


Discover more from SAY NO TO THE DESTRUCTION OF OUR LAND

Subscribe to get the latest posts sent to your email.