2010: COSTS WERE FORECAST. 2015: DEDICATED REPORTING WAS WITHDRAWN. 2026: NEW INQUIRIES.
The regulator’s job is not simply to approve a programme of investment. It must protect consumers by testing costs, performance and the benefits claimed for that expenditure. The historical record matters because the risks of connecting generation before wider reinforcement were identified when the policy was adopted.
In Wednesday’s opening investigation, we examined the £443 increase in the annualised price cap, from £1,723 to £2,166. Ofgem’s confirmed cost breakdown attributes the immediate increase principally to wholesale costs: the wholesale allowance rose 50%. The system costs investigated here are a separate structural pressure. They must not be presented as the cause of the whole January increase. Ofgem, 25 November 2026: cost breakdown.
2014 — THE COST WARNINGS WERE ALREADY MATERIALISING
CONNECT AND MANAGE — POLICY-ATTRIBUTED ANNUAL CONSTRAINT COSTS
2012/13 — £22.2m
2013/14 — £69.4m
Specific costs attributed to the access regime, not all system constraint or balancing expenditure. Ofgem fifth report and letter to Matthew Hancock, December 2014.
By December 2014 the regulator had reported a more than threefold rise in the annual constraint costs attributed to the policy. That is important because these figures do not merely describe a general rise in energy prices. They concern the identified costs of the access arrangements themselves. A year later ministers were still discussing uncertain generation and major reinforcement schemes that had not started. The next question is what decisions followed those warnings.
2015 — WHY WAS DEDICATED REPORTING WITHDRAWN WHILE RISKS REMAINED?
DECEMBER 2015 — THE REPORTING REQUIREMENT WITHDRAWN
14 DECEMBER
Ofgem sixth monitoring report
21 DECEMBER
Minister Andrea Leadsom’s response
ANNUAL REPORTING
Dedicated government requirement withdrawn
The minister recognised uncertainty over future generation and unstarted reinforcement. This is not evidence that all subsequent monitoring ceased. Source: DECC ministerial letter, 21 December 2015
On 21 December 2015, Andrea Leadsom replied to Ofgem’s sixth monitoring report. The letter noted uncertainty over generation coming forward and the completion of major reinforcements not yet started. It also asked whether investment could be brought forward and queue management improved. The same letter withdrew the requirement for annual reports to government on the regime’s operation.
This was a ministerial decision, not a unilateral decision by Ofgem. It does not establish that monitoring ceased; oversight could have continued through industry governance, price controls and other reporting. The specific accountability question is which mechanism replaced the dedicated reports, what evidence was available to ministers and whether the forecast assumptions were reconsidered in time. Read the original signed response. Ofgem sixth monitoring report.
2021 — ENFORCEMENT SHOWS HOW DELAYS REACH BILLS
WESTERN LINK — A DOCUMENTED CASE
2,250 MW
Transfer capacity
MARCH 2017 → JUNE 2019
Original expected delivery and actual completion
£158 MILLION
Agreed consumer redress package in 2021
Joint NGET/SPT licence responsibility. Ofgem found supply-chain delays, not that the two companies caused or exacerbated them. Source: Ofgem, 30 November 2021
Ofgem did intervene in the Western Link case, and the agreed redress matters. It demonstrates why there must be a public project-level account of delays, allowances and cost consequences. It does not establish that enforcement was absent throughout the period.
2026 — THE REGULATOR HAS OPENED NEW INQUIRIES
On 17 April 2026, the joint DESNZ and Ofgem letter acknowledged significant programme delays caused by errors in historic connection agreements and the need to repeat network studies. Seven months later the regulator opened an urgent inquiry into later offers for protected and Phase 1 projects. These are two separate admissions of delivery problems, not proof that every delayed scheme shares the same cause. Read the joint April letter.
On 19 November, Ofgem announced an urgent inquiry into why numerous protected and Phase 1 projects had been offered dates later than their pre-reform offers, despite queue reform. It explicitly recognises that the causes may differ between projects. The inquiry is evidence of an unresolved delivery problem, not a concluded finding of misconduct. Ofgem inquiry announcement.
The regulator’s technical review of June’s extreme heat event is separate. It is examining the system operator’s performance and the security of the network. Publication of the findings and corrective actions will matter more than reassuring statements alone. Ofgem regulatory review.
TRANSMISSION CHARGES — MORE THAN DOUBLE
Annual transmission network charges, constant 2025 prices
2025/26 — £5.1bn
2030/31 forecast — £12.3bn
Real increase of approximately 141%. Annual regulated charges, not the £70bn cumulative investment programme.
If costs are rising in the near term while claimed savings depend on later grid completion, the consumer needs to see the evidence for both. Ofgem’s price-cap decision also shows wholesale allowance increases: the structural cost investigation must not obscure that immediate driver.
THE 20p ASSURANCE — AND THE WARNINGS THAT FOLLOWED
In July 2010, the Department of Energy and Climate Change published its decision on a new approach to grid access: Connect and Manage.
THE FORECAST. THE REALITY.
Total GB constraint management costs, 2010–2020 (net present value)
Original government forecast — ~£1bn
Actual costs — ~£3bn
Three times the forecast. Both figures are total constraint costs in NPV terms; the original 20p household assurance measured a different, incremental policy cost.
Source: FTI / Energy Systems Catapult, October 2023, p. 74, para 3.24
The policy allowed generators to connect earlier, without waiting for all the wider transmission reinforcement that would previously have been required. The intended benefits were earlier access to generation and improved security of supply. The foreseeable consequence was greater congestion in parts of the network.
The Government’s central estimate was around 20p per household per year in additional costs, with around £1 under its extreme scenario. Those figures referred to the incremental impact of the policy, not the entire cost of balancing Britain’s grid.
The same consultation record shows that Ofgem had raised concerns about the proposed arrangements. It was not simply silent. In later years it produced monitoring reports, including its sixth report in December 2015.
By 2023, parliamentary evidence was explicitly identifying Connect and Manage as a contributor to rising constraint costs because generation had been allowed onto the system before the grid could transport all its power.
Today, NESO records approximately £2 billion of annual thermal constraint costs and warns of substantially higher costs under certain 2030 scenarios.
We cannot honestly compare the entire current constraint bill with the original 20p incremental estimate as though they are the same measurement. What we can ask is why the assumptions were so far removed from the congestion pressures that subsequently emerged, what corrective actions were taken, and how much additional expenditure could have been avoided.
Ofgem’s core statutory purpose is to protect the interests of existing and future consumers. Its duties also include supporting the transition to net zero. These responsibilities must be reconciled in actual expenditure decisions, not merely stated in policy documents.
The public deserves a transparent account of the trade-offs: the costs of earlier generation access, the benefits secured, the regulated expenditure approved, the delivery performance of transmission owners and the consequences when original forecasts prove wrong.
That is the accountability question at the heart of this series.
On Sunday, we bring together the decisions, the institutions and the financial evidence in one consolidated account.
Evidence: DECC July 2010 government response; Ofgem sixth monitoring report; 2023 Parliamentary report; NESO projections.
Petition: Read and sign Parliamentary petition 780321.
Shane Oxer — Campaigner for fairer and affordable energy